Service assignment at TERRENERGIES 360 in Terminiers (FR)
A recent service call at the TERRENERGIES 360 biogas plant south of Paris shows how important fast technical support is in plant operation.
In spring 2026, EnvironTec was involved in the commissioning of a gas flare at the Haigerloch wastewater treatment plant in the Lower Eyachtal valley (Germany). The plant is part of a regional wastewater network and treats wastewater from several municipalities and districts around Haigerloch, Empfingen and Horb.
On site, service technician Rene Krebs was responsible for the complete commissioning of the FAII 50 gas flare, including connection piping and installation. After delivery in November 2025, the final commissioning took place at the customer’s premises on April 2, 2026.
The work carried out included connecting the gas supply lines, setting up and fixing the flare and installing the control cabinet in an external position. In addition, all sensors were connected, a comprehensive leak test was carried out and all switching elements were tested. A final test run confirmed that the system was functioning perfectly.
With the successful implementation, EnvironTec is making an important contribution to the safe incineration of excess sewage gases from wastewater treatment in the Lower Eyachtal and thus supporting the reliable operation of the plant.

A recent service call at the TERRENERGIES 360 biogas plant south of Paris shows how important fast technical support is in plant operation.

Exceptional project in southwest France: In Cognac, a new FAII 1500V gas flare ensures the safe utilization of sewage gas and biogas.

As part of a targeted service assignment, a Bilgeri Environtec specialist was on site at the WWTP Tampere wastewater treatment plant in Finland 24 hours after the service request …

The IDA Merano high-performance wastewater treatment plant in South Tyrol commissioned a new FAII 1000v gas flare from Bilgeri Environtec in November 2025.

The joint sewage treatment plant in Bitterfeld-Wolfen (Saxony-Anhalt) once again relies on Bilgeri EnvironTec – a new FAII 750 was put into operation in September 2025.

A new FAII 100 emergency gas flare from Bilgeri Environtec was put into operation at the Vyskov wastewater treatment plant (Czech Republic) in September 2025.